Can you build an ADU in Cobb County? Yes, in unincorporated Cobb, with Board approval. On October 27, 2026, the Cobb County Board of Commissioners adopted code amendments that allow one accessory dwelling unit on a single-family lot as a special land use permit use in the R-80, RR, R-40, R-30, R-20, R-15 and R-12 districts[1]. The ADU must sit in the rear yard, stay within 50 percent of the main house’s gross square footage or 850 square feet, occupy one floor, stay no taller than the main house, have at least one off-street parking space, and connect to the main house’s utility meters. The owner must live on the property, and short-term rentals are not allowed[1].
Key Takeaways
- New option, adopted October 27, 2026. Cobb’s Chapter 134 zoning amendments now define an ADU and allow one per single-family lot[1][2].
- Every detached ADU goes to a hearing. ADUs are a special land use permit use in seven single-family districts, so the Board of Commissioners decides each case[1].
- Small and behind the house. Rear yard only, 50 percent of the main house or 850 square feet, one floor, no taller than the main house[1].
- Shared utilities. The ADU connects to the main house’s utility meters[1].
- Owner on site, no short-term rentals. The owner lives in the house or the ADU, and neither can be a short-term rental[1].
- Covenants still count. The applicant signs an affidavit that the ADU does not conflict with covenants, deed restrictions or HOA bylaws[1].
- The site plan carries the application. Cobb asks for a stamped plot plan and boundary survey with every special land use permit application[5].
What Cobb County Changed on October 27, 2026
Cobb’s 2026 code amendment package went through a Planning Commission hearing on October 6 and Board of Commissioners hearings on October 13 and October 27, and the Board adopted it on October 27[1][2]. The county’s final summary of revisions shows no changes to the ADU standards between the October 21 draft and adoption[3]. News coverage reports the ADU amendment passed 3 to 2[8][9].
What an ADU is under Cobb’s code
The adopted definition calls an ADU a residential dwelling unit subordinate to the principal single-family dwelling on the same lot, and it can be attached to or detached from the main house. The code also says one single-family dwelling unit includes the main house and may include up to one ADU[1]. Cobb’s own summary describes an ADU as a smaller, separate home that could house a family member, caregiver or other household member[4].
Why detached cottages are now possible
Before this change, Cobb’s accessory structure rules required any habitable accessory building to be attached to the main house by a fully enclosed, heated and cooled hallway, within 25 feet of the house. The adopted amendments strike that rule from each single-family district[1]. That is what opens the door to a true backyard cottage. The Marietta Daily Journal reports that attached units sharing the main entrance were already allowed[11]; under the new code, an ADU with its own separate entry requires a special land use permit[1].

Cobb County ADU Requirements at a Glance
The table below reflects the Chapter 134 amendments Cobb County adopted on October 27, 2026, as posted by the county in November 2026. Confirm current requirements with the Cobb Zoning Division before you apply.
| Requirement | Adopted Cobb rule | What it means for your site |
|---|---|---|
| Approval | Special land use permit in R-80, RR, R-40, R-30, R-20, R-15 and R-12; separate-entry ADUs require one[1] | A public hearing and a Board vote, decided on the site plan you submit |
| Size | Not more than 50% of the main house’s gross square footage or 850 sq ft[1] | Plan to the smaller number; a 1,400 sq ft house points to 700 sq ft |
| Height and floors | One floor of the accessory structure; no taller than the main house[1] | Ranch-style main houses limit roof height on the ADU |
| Location | Rear yard only; side and rear setbacks of the main house[1] | Lot depth, slope and trees decide whether it fits |
| Accessory structure standards | All other accessory structure standards for the district still apply[1] | Check size thresholds, corner-lot rules and design approval early |
| Impervious coverage | Lot may not exceed the district’s maximum[1] | Roof, slab, walks and the new parking space all count toward the limit |
| Parking | At least one off-street space for the ADU; lot-wide limits in Sec. 134-1 apply[1] | Driveway layout, grading and runoff from new paving |
| Utilities | Connected to the main house’s utility meters[1] | Water, sewer or septic, and power run from the main house |
| Number | One ADU per single-family lot[1] | No second unit or duplex layout |
| Occupancy and rental | Owner lives in the house or ADU; no short-term rental of either[1] | Plan for family, caregiver or long-term household use |
| Covenants | Applicant signs an affidavit of no conflict with covenants, deed restrictions or bylaws[1] | Read your HOA documents before paying for design |

Where the Cobb County ADU Rules Apply
The new rules cover unincorporated Cobb County only. The adopted summary of uses lists an ADU as a special land use permit use in the R-80, RR, R-40, R-30, R-20, R-15 and R-12 single-family districts[1]. If your lot carries a different zoning, ask the Zoning Division how the rules apply before you go further.
Cities in Cobb write their own zoning rules. The Marietta Daily Journal reports that Acworth, Mableton, Marietta and Powder Springs already allow ADUs[10]. For rules in other Metro Atlanta cities and counties, see our Georgia ADU permit guide.
Check your covenants first
Cobb’s approval does not override private restrictions. The adopted code says an ADU shall not conflict with applicable covenants, conditions, deed restrictions or bylaws, and the applicant signs an affidavit saying so with the application[1]. Many East Cobb and West Cobb subdivisions have recorded covenants, so read them before you spend money on design.

How the Special Land Use Permit Process Works
A special land use permit is a zoning decision, not a counter permit. Applications are advertised and heard the same way as rezoning cases, and Cobb staff analyses state that the granting of a special land use permit is conditional upon the site plan considered by the Board[7]. The Board weighs fifteen criteria, including compatibility with the neighborhood, effects on surrounding properties, adequacy of parking and traffic, and whether the application meets the specific requirements for that use[7].
What the application asks for
Cobb’s posted special land use permit application lists what goes into a complete package[5][6]:
- A plot plan and current boundary survey drawn to scale and stamped by a registered engineer, architect, land planner or land surveyor, showing lot lines, adjoining streets and right-of-way, the size and location of all buildings, parking spaces, utility easements, floodplain, streams and stream buffers, wetlands and access points[5].
- A statement of proposed site improvements, such as grading, tree removal, paved parking and detention[5].
- Health Department approval before filing if the property is or will be on septic[5].
- Ownership documents, a legal description, proof of paid taxes and a petition form for neighboring owners[5].
- Zoning signs posted on the property before the hearing, and attendance at the hearing by the applicant or a representative[5].
The posted application describes a monthly filing cutoff, with cases heard first by the Planning Commission and then by the Board of Commissioners[5]. Check the current schedule and fees on the Zoning Division’s forms and schedules page before you file. Our permit application management team can organize the package and track it through review.
Site Issues That Decide Whether an ADU Fits Your Lot
Most Cobb ADU questions are answered on the site plan, not the floor plan. These are the items we check first. Our post on what to evaluate before you design an ADU covers the same questions in more depth.
Rear yard, setbacks and accessory structure size
The ADU must sit in the rear yard and meet the side and rear setbacks of the main house, and it must also meet the district’s other accessory structure standards[1]. Those standards include size thresholds: accessory buildings over 650 gross square feet must be at least 100 feet from any property line and go through plan review, and the building’s architecture must be approved by the zoning division as complementary to the main house[1]. How the 650 square foot threshold applies to an ADU is a question to settle with zoning staff before design, because it can change where the cottage goes on a typical lot.
Impervious surface and drainage
The lot’s total impervious coverage cannot exceed the district limit[1][4]. The ADU roof, slab, walks and the new parking space all add up. New hard surface also sends more runoff toward the back and sides orom the main house to the cottage. We check whether the sewer line can flow by gravity from the rear yard, where the service lines can cross the lot without conflicting with trees or easements, and whether an existing septic system needs Health Department review, which Cobb requires before a special land use permit application is filed[5].

How Mack Engineering Helps With a Cobb County ADU
Because every Cobb ADU is decided on its site plan, the engineering work comes first. Mack Engineering offers professional engineering in Georgia from our office in Alpharetta, and we support homeowners, builders and designers at each step:
- Feasibility before design. A site feasibility report checks zoning, setbacks, impervious coverage, slope, utilities and covenants so you know whether the ADU fits before paying for architecture.
- Special land use permit exhibits. We prepare the scaled site plan exhibit the application requires, built on a current boundary survey, and help you present the layout clearly at the hearing. Learn more about our zoning and land use planning services.
- Site planning. Site planning that places the cottage, walkway and parking space within the rear yard and setbacks.
- Grading and drainage. Grading, drainage and erosion control plans that handle runoff from the new roof and paving.
- Utilities. Water, sewer and septic layouts tied to the main house’s meters, with service routes that avoid trees and easements.
- Coordination. We work with your architect, designer or builder, and we model in Revit when a 3D view helps the team resolve the site and building together.

Our Cobb County ADU Process
- 1. Lot review: zoning district, setbacks, rear-yard depth, slope, trees, floodplain, streams, easements and covenants.
- 2. Feasibility: the ADU size the code allows for your house, impervious coverage, parking and utility routes.
- 3. Site plan exhibit: a scaled plan for the special land use permit application that shows the ADU, parking, utilities and drainage.
- 4. Application and hearing: a complete package for the Zoning Division and support through the Planning Commission and Board of Commissioners hearings. See our permit application management services.
- 5. Construction documents: grading, drainage, erosion control and utility plans for permitting once the Board approves the request.
- 6. Construction support: answers to field questions so the cottage is built where the approved site plan shows it.

Plan Your Cobb County ADU With Mack Engineering
Thinking about a backyard cottage, in-law suite or caregiver unit in unincorporated Cobb? Send us your address, a survey if you have one, and your goals. We will tell you what the county’s ADU rules allow on your lot and what the special land use permit application will need. Contact Mack Engineering or call (770) 715-7295.
Frequently Asked Questions
Can I build an ADU in unincorporated Cobb County?
Yes. On October 27, 2026, the Cobb County Board of Commissioners adopted code amendments that allow one accessory dwelling unit on a single-family lot. In the R-80, RR, R-40, R-30, R-20, R-15 and R-12 districts, an ADU is a special land use permit use, so each one needs approval from the Board at a public hearing before it can be built.
How big can an ADU be in Cobb County?
The adopted code says an ADU shall not exceed 50 percent of the gross square footage of the main house or 850 square feet. Plan to the smaller of the two numbers. For example, a 1,400 square foot house points to a 700 square foot ADU. The ADU can occupy only one floor of the accessory structure and cannot be taller than the main house.
Do I need a special land use permit for an attached in-law suite?
The adopted code requires a special land use permit for an ADU accessed from a separate entry. Local news coverage reports that attached units sharing the main entrance were already allowed before the change. Confirm your layout with the Cobb Zoning Division before you design.
Can I rent out an ADU in Cobb County?
Not as a short-term rental. The adopted code bars short-term rental of both the main house and the ADU, and the owner must live in either the main house or the ADU. The county’s occupancy and parking limits apply to the house and ADU together.
What does an engineer prepare for a Cobb County ADU application?
Cobb’s special land use permit application asks for a plot plan and boundary survey drawn to scale and stamped by a registered engineer, architect, land planner or land surveyor, showing items such as buildings, parking, easements, floodplain, streams and access points. Mack Engineering prepares the site plan exhibit and the grading, drainage and utility planning that support it.
Does the Cobb County ADU ordinance apply inside cities like Marietta?
No. The new rules apply to unincorporated Cobb County. Cities set their own zoning rules, and news coverage reports that Acworth, Mableton, Marietta and Powder Springs already allow ADUs. If your lot is inside a city, check that city’s code.
Sources
[1] Cobb County Community Development, 2026 Code Amendments, Official Code of Cobb County, Part I, Chapter 134 (Zoning), Package I, adopted October 27, 2026. https://assets.cobbcounty.gov/files/2026-10/2026%20Oct%20Chapter%20134%20Final.pdf
[2] Cobb County, Code amendments to be reviewed in October 2026 (final approved code amendments). https://www.cobbcounty.gov/news/code-amendments-reviewed-october-2026
[3] Cobb County, 2026 Code Amendments Summary of Revisions (Final). https://assets.cobbcounty.gov/files/2026-10/2026%20Code%20Amendments%20Summary%20of%20Revisions%20FINAL.pdf
[4] Cobb County, Proposed Housing and Neighborhood Code Updates, Explained. https://www.cobbcounty.gov/news/proposed-housing-neighborhood-code-updates-explained
[5] Cobb County Zoning Division, Special Land Use Permit Application and Schedule. https://assets.cobbcounty.gov/files/2024-12/2025%20Special%20Land%20Use%20Permit%20Application%20and%20Schedule.pdf
[6] Cobb County Zoning Division, Zoning Forms and Schedules. https://www.cobbcounty.gov/community-development/zoning-division/zoning-forms
[7] Cobb County Zoning Division, Zoning analysis for SLUP-1 (2018), showing the special land use permit criteria. https://zoning.comdev.cobbcountyga.gov/2018-03/final_zoning_analysis/SLUP-001-2018-(District%203-325%20Chastain%20Road).pdf
[8] Marietta Daily Journal, Cobb approves accessory dwelling units, new data center rules (October 28, 2026). https://www.mdjonline.com/news/local/cobb-approves-accessory-dwelling-units-new-data-center-rules/article_9130a8a6-f0e9-4ccb-ae89-f0066046596a.html
[9] East Cobb News, Cobb passes ordinance allowing accessory dwelling units (October 30, 2026). https://eastcobbnews.com/cobb-passes-ordinance-allowing-accessory-dwelling-units/
[10] Marietta Daily Journal, Cobb County proposes zoning code change to allow ADUs (September 9, 2026). https://www.mdjonline.com/news/local/cobb-county-proposes-zoning-code-change-to-allow-adus/article_3d55b05d-ae55-46e7-9b1b-3d26a16eef6c.html
[11] Marietta Daily Journal, ADUs, to-go cocktails and vape shops: What code changes is Cobb County proposing? (October 25, 2026). https://www.mdjonline.com/news/local/adus-to-go-cocktails-and-vape-shops-what-code-changes-is-cobb-county-proposing/article_74ef41d9-d0a4-4118-a08d-ebbb7cc84a45.html